herhaling van gisterenavond
Winners named for 3€bn London Super Sewer
Aaron Morby | Fri 27th February | 7:07
inShare
Email
Thames Tideway Tunnel project chiefs have picked the preferred construction consortia to drive three major tunnel sections of the London Super Sewer.
A joint venture between Laing O’Rourke and Ferrovial Agroman has landed the largest Central section drive worth 826€m-1 239€m.
The Eastern section of the tunnel has been bagged by a Costain, Vinci and Bachy joint venture and is expected to cost 688€m-1 101€m.
Another three-way consortium consisting of Balfour Beatty, BAM Nuttall and Morgan Sindall has picked up the shorter western tunnel drive, which is expected to be worth somewhere between 413€m-688€m.
Thames Tideway
Contracts are expected to be formally awarded in the summer, when the investors chosen to finance and deliver the project are revealed.
The trio of winning consortia each bid for all three sections of the 7.2m tunnel which will be driven 24km under much of the Thames from Acton in West London to Abbey Mills in the east.
Innovative engineering in the design phase has already reduced the tunnel from the initial 32km proposed, down to 25km, and reduced the number of construction sites needed from 45 to 24.
The tunnels will be dug with a gently sloping gradient, falling 1m for every 790m its travels up to 60m below the surface.
Under the present programme, construction is expected to start in 2016 and conclude in 2023.
Several major foreign contractors paired off and opted to bid just one section. But this strategy looks to have failed to pay off.
Disappointed bidders targeting the eastern section, include Bouygues which went it alone, a joint venture between Hochtief and Murphy and a Bechtel/ Strabag pairing.
A Dragados/Samsung joint venture bid for the west section, while Skanska teamed up with Bilfinger and Razel Bec was hoping for the prized central section.
The total Thames Tideway Project is estimated to cost around 6€bn at 2011 prices. Around 2€bn of the Thames Tideway Tunnel’s construction cost will be financed by Thames Water and 4€bn by Thames Tideway Tunnel Ltd.
Thames Water’s contribution will fund development costs, enabling works and interface works.
Thames Tideway